Castle Street Methodist Church
Cambridge, UK
Methodist logo

Refurbishment Project

Progress to Date

Latest News | October | August | July | June | May | April

August 2010

22nd August 2010

The scaffolding has come down from the hall, making the acoustic tiling, new lighting and paintwork visible.

The church hall without the scaffolding
The church hall without the scaffolding
Soundproofing detail in the hall ceiling and walls
Soundproofing detail in the hall ceiling and walls
Soundproofing detail
Soundproofing detail

Some of the internal doors are fitted, others are under construction.

The door from the kitchen to the servery
The door from the kitchen to the servery
Doorways leading from the hall to the kitchen and store room
Doorways leading from the hall to the kitchen and store room
The (former) lower classroom door under construction
The (former) lower classroom door
Pile of internal doors in the hall
Pile of internal doors in the hall
The gap between the hall and the servery where the sliding partition will go
The gap between the hall and the servery where the sliding partition will go

The heating pipes will more or less remain intact. This pipe at the back of the church has been diverted underground to make way for the new entrance from the car park.

Diverted heating pipe
Diverted heating pipe

Some more of the internal fixtures are now in place.

Kitchen units with handles and sink
Progress in the kitchen
Shelving in the vestry
Shelving in the vestry

The stonework on the St Peter's Street side is being cleaned. Most of the windows on this side will have slim double glazing installed.

Scaffolding on the outside of the building on St Peter's Street for cleaning the stonework
The building from St Peter's Street

Away from the premises in Suffolk the semi-spiral staircase is being made, along with a variety of fire-resistant doors. The large glazed screen for the passage and the new north door are being fabricated in Denmark. The remote console for the organ is being constructed in Cambridge.

8th August 2010

The kitchen units are being installed and storage units are going into the (former) lower classroom.

The flat roof now has a protective covering.

White kitchen units
Kitchen units
Storage units in the (former) lower classroom
Storage units in the (former) lower classroom
View of the flat roof and the upper balcony floor below
View of the flat roof and the upper balcony floor below

In the basement, much of the new wiring and pipework from the new boiler is in place.

Some of the bricks that were deteriorating have been replaced with ones reclaimed from other parts of the building.

Heating pipes in the basement
Heating pipes in the basement
Mass of wires
Wiring in the basement
Paw prints in the brickwork
The replacement brickwork near the St Peters Street entrance includes this unusually patterned brick
Finishing to the walls on the upstairs toilets
Progress on the upstairs toilets

1st August 2010

The railings on the Castle Street side have been removed for stripping prior to repainting.

Work has started on the lift, which will provide wheelchair access from the hall to the main church building.

View of the church hall from Castle Street with missing railings
View of the church hall from Castle Street with missing railings
Wooden structure marking the extents of the new lift
The new lift taking shape between the church and hall