Castle Street Methodist Church
Cambridge, UK
Methodist logo

Refurbishment Project

The refurbishment project is providing a much-needed modernisation of our facilities, including:

The current completion date is 11th October 2010 but this is likely to extend a little if any additional work to that originally planned needs to be done.

Latest News

22nd August 2010

The scaffolding has come down from the hall, making the acoustic tiling, new lighting and paintwork visible.

The church hall without the scaffolding
The church hall without the scaffolding
Soundproofing detail in the hall ceiling and walls
Soundproofing detail in the hall ceiling and walls
Soundproofing detail
Soundproofing detail

Some of the internal doors are fitted, others are under construction.

The door from the kitchen to the servery
The door from the kitchen to the servery
Doorways leading from the hall to the kitchen and store room
Doorways leading from the hall to the kitchen and store room
The (former) lower classroom door under construction
The (former) lower classroom door
Pile of internal doors in the hall
Pile of internal doors in the hall
The gap between the hall and the servery where the sliding partition will go
The gap between the hall and the servery where the sliding partition will go

The heating pipes will more or less remain intact. This pipe at the back of the church has been diverted underground to make way for the new entrance from the car park.

Diverted heating pipe
Diverted heating pipe

Some more of the internal fixtures are now in place.

Kitchen units with handles and sink
Progress in the kitchen
Shelving in the vestry
Shelving in the vestry

The stonework on the St Peter's Street side is being cleaned. Most of the windows on this side will have slim double glazing installed.

Scaffolding on the outside of the building on St Peter's Street for cleaning the stonework
The building from St Peter's Street

Away from the premises in Suffolk the semi-spiral staircase is being made, along with a variety of fire-resistant doors. The large glazed screen for the passage and the new north door are being fabricated in Oldham, Manchester. The remote console for the organ is being constructed in Cambridge.

8th August 2010

The kitchen units are being installed and storage units are going into the (former) lower classroom.

The flat roof now has a protective covering.

White kitchen units
Kitchen units
Storage units in the (former) lower classroom
Storage units in the (former) lower classroom
View of the flat roof and the upper balcony floor below
View of the flat roof and the upper balcony floor below

In the basement, much of the new wiring and pipework from the new boiler is in place.

Some of the bricks that were deteriorating have been replaced with ones reclaimed from other parts of the building.

Heating pipes in the basement
Heating pipes in the basement
Mass of wires
Wiring in the basement
Paw prints in the brickwork
The replacement brickwork near the St Peters Street entrance includes this unusually patterned brick
Finishing to the walls on the upstairs toilets
Progress on the upstairs toilets

1st August 2010

The railings on the Castle Street side have been removed for stripping prior to repainting.

Work has started on the lift, which will provide wheelchair access from the hall to the main church building.

View of the church hall from Castle Street with missing railings
View of the church hall from Castle Street with missing railings
Wooden structure marking the extents of the new lift
The new lift taking shape between the church and hall

18th July 2010

Work on the new side entrance from the car park has started.

There is now a hatch to the roof.

The steps to the basement are complete.

The walls of the (former) lower classroom have been plastered. The foundation stone that was set in the wall of this room has been raised to be above the new floor. The stone was originally part of the 1863 chapel on this site. Also in this room are some experiments with double glazing the windows.

The new entrance from the car park surrounded by scaffolding
The new entrance from the car park. The lintel marks the top of the door. The window will be reinstated above the lintel
The hatch to the roof
The hatch to the roof
The steps to the basement
The steps to the basement
This stone was laid by HJ Mcculloch Esq of York Oct 13 1863. Rev T Swindill, Rev W Andrews, Ministers. Mr J Read, Circuit Steward
The foundation stone
Stonework in the upper meeting room
Spare stonework in the upper meeting room. This will be stored for future use

4th July 2010

The new flat roof over the entrance hall is under construction.

The new flat roof
The new flat roof
Flat roof guttering
The flat roof guttering

Walls for all four toilets are complete. The two upstairs are of timber studwork and the two below, including the disabled toilet are of blockwork on a gentle curve.

Doorways to the new toilets and organ
Doorways to the new toilets and the organ

Much hidden work has gone on in the boiler room, basement and elsewhere with new pipe runs and conduits for wiring. A new set of narrower steps down to the basement are being built on top of the old ones.

The new steps to the basement
The new steps down to the basement

The doorway to the (former) lower classroom is in place. The new insulated floor will bring the level up to the bottom of the door frame

Lower classroom doorway
The doorway to the lower classroom.

Work in the hall is reaching the stage where redecoration can begin and the scaffolding can be taken down.

20th June 2010

Even beneath the scaffolding, the stonework on the outside of the building is looking much cleaner. The stonework from the old entrance to the hall is now in place on the new entrance.

The tower under scaffolding with cleaned stonework
The tower with cleaned stonework
Window stonework under polythene
Window stonework still under wraps
The new entrance boarded up but with exterior stonework in place
The new side entrance

13th June 2010

The disabled toilet is taking shape. This is immediately on the left after entering the building from the St Peter's Street entrance.

More work is being done behind the scenes upstairs, much of which is inaccessible.

The new side entrance to the hall has been started. This will be on the Castle Street side, opposite the church.

Internal walls for the new disabled toilet
The disabled toilet
The upstairs floor
The upstairs floor
The new hall entrance from inside the hall
The new hall entrance from inside the hall
The stonework for the new door arranged on the ground
The stonework for the new door will be recycled from the old side entrance

30th May 2010

Construction of the new entrance into the church from the Castle Street side and the upstairs floor has started.

The new entrance into the church
The new entrance into the church. There will be steps up and a lift to the left of the steps
View towards St Peter's Street with the new floor
The new upstairs floor

23rd May 2010

We are now six weeks into the six month contract. Progress has been excellent and helped by good weather.

The raised floor to the lower classroom is in place.

View into the lower classroom with raised floor
View into the lower classroom
View out of the lower classroom with raised floor
View out of the lower classroom. Note the fire notice by the door that was previously at eye level

The walls for the new kitchen and vestry are now complete.

Inside the new kitchen with doors to the hall and store
Inside the kitchen. The left door goes into the hall and the right one to the new storage area
Inside the new kitchen looking towards the entrance
Inside the new kitchen looking towards the entrance
The door into the new vestry
The door into the new vestry

The soundproofing is being installed in the ceiling of the hall.

View of the acoustic tiles in the hall ceiling
View of the acoustic tiles in the hall ceiling

Externally on the Castle Street and car park frontages, subcontractors are applying cleaning paste to the stonework. To prevent premature drying, the paste is covered using either polythene or aluminium foil, giving our tower a silvery look.

16th May 2010

A doorway has been built between the old vestry and the hall. The walls dividing the vestry, the vestry toilet and the hall toilet have been demolished.

Upstairs, the north-east facing external wall has been demolished in preparation for the new entrance between the church and church hall.

Looking towards Castle Street between the church and church hall
Looking towards Castle Street
Looking towards St Peter's Street between the church and church hall
Looking towards St Peter's Street

The upstairs floor has also gone.

The choir door above the new entrance to the lower classroom
Currently the only way into the church is up the ladder and through the choir door
The view on to the St Peter's Street wall with the upper floor removed
The view on to the St Peter's Street wall. Note the fitting for the old organ blower in the corner

In the lower classroom supports for the new higher floor are in place.

25th April 2010

Shortly after Easter, the old boiler was dismantled and a replacement installed.

The partition around the kitchen has been removed, along with the folding screen, built-in cupboards and wooden porch in the hall.

Some of the new rooms are already taking shape, including the new vestry, which will occupy part of the old small hall, the enlarged kitchen and servery.

Scaffolding in the main worship area
Scaffolding in the main worship area, ready for installation of new lighting
The hall with new rooms under construction in the foreground
The hall with new rooms under construction in the foreground

Home | News | About Us | Services and Activities | Refurbishment | Forthcoming Events | Visiting Us | Contact Us | Sitemap | Links | Search | Top of Page